Approval Center Mismatch
Hi All, When I open the home page of PWA 2010, I see 61 tasks pending for Approval. But when I click on the Approval center, there are no tasks for Approval. What could be the problem?Cheers, Amit Wairkar
View ArticleCan I have the publish button enabled on the same page where status updates...
Can I have the publish button enabled on the same page where status updates are visible?
View ArticleDynamic Workflow - Portfolio Analysis Commit issue
Hi, We have downloaded the Dynamic Workflow July 2012 version and created one workflow using it. The proposal is stuck at the Portfolio Analysis stage after commit. i have checked the Reporting...
View ArticleStatus updates history will not display - Error, an unhandled exception...
Hi, When I go to PWA -> Approval Center -> History -> Status Updates I get the following error instead of the normal grid: An unhandled exception occurred in...
View ArticleCannot open Resource Calendar
Hi All We are using Project Server 2010 and facing a issue with function in Resource Center. I would like to ask if somebody can give some advice how to get this fixed. We are importing resources...
View ArticleTasks created using PSI has incorrect duration
Hi, I'm using the following code to create projects tasks within workflow using PSI. The start date and end date that I'm using to create tasks are "Start Date: 8/7/2012" and "End Date: 8/15/2012" so...
View ArticleZero-out Remaining Work in Project Server 2010 with SEM enabled, and Protect...
Hello All, We are using Project Server 2010 +SP1 + Jun 2012 CU. We have following settings in our environment: - SEM (Single Entry Mode) Enabled - In "Task Settings and Display > Project User...
View ArticleReporting Web Part Error
Hi everybody! I have the following issue with SQL Server Reporting web part. The project farm configuration is as follows: Server A - Project Server 2010 + SQL Server 2008 R2 SP1 Server B - separate...
View ArticleRead-only in MS Project but can read-write in PWA
I have a user who has 'full' permissions as a resource in Project Server 2010. For three months he was able to edit projects in PWA as well as MS Project. For some reason, he can now only edit (i.e....
View ArticleWorkflow Approval Task not being created as PSWApprovalTask content type
We are in the process of deploying Project Server into our organization. We have developed a custom workflow that requires approvals. In the development environment when these workflow approvals are...
View ArticleTimeTracking - Actual Costs on the actual day
Hi everyone, we are using Project Server 2010, where each project member reports their time using the Timesheet function. This way we update the tasks and the actual costs for a project. But sometimes...
View ArticleIssues and Risks do not contains items in PWA site
Hi All, I am facing very wierd issue. When I am adding items in Issue list and Risk list in a Project's workspace site, I should see all tasks assigned to me in PWA site under My Work -> Issues and...
View ArticleBulk Edit "Earliest Available" and "Latest Available"
We have the need to add "Earliest Available" and "Latest Available" dates to the ERP (MSPS 2010). Many resources will share the same dates. I am looking for a way to quickly do this without having...
View ArticleStatus Report Templates
Several Questions: 1) Is there a way to create a status report template? 2) Rather than have to send out a request for status reports, can individuals just submit a status report each week using the...
View ArticleEnterprise calendar and resource calendar
Hi all, I have several questions. 1. Is it possible to somehow link the internal corporate sharepoint calendars with calendars in PWA? 2. If not, how you can display in PWA enterprise calendar...
View ArticlePWA2010 - Approved timesheets not reflected in Project Plan
We have installed Project Server 2010 and are using PWA to record time against tasks using timesheets. For over a month now, any tasks that are approved by the PM are not being updated in the project...
View ArticleTimesheet Save / Submit issue
Hi I am working as administrator for EPM 2010. Few resources cant Save / Submit the timesheet, the screen is showing still loading (progress bar). I have performed below activities to resolve the...
View ArticleLookup Table value vs. description
I have PWA 2010 and Project Pro 2010. I have a enterprise custom field with a enterprise lookup table. How do I get the lookup table description to show up when I group on it in Project Pro 2010?...
View ArticleFilter the Task List When Linking Issues and Risks to Project Tasks
This question is regarding Project Server 2010. In a project workspace within PWA, there is a nice feature that will allow you to create issues and risks and link them to specific tasks within the...
View ArticleRequired custom enterprise fields - showing as required for PDP pages that...
As the title implies, I have several required custom enterprise fields, along with 4 PDPs that contain all my required and non-required fields. I have 2 EPTs that use the associated PDPs. Here is the...
View Article