Hi everyone,
we are using Project Server 2010, where each project member reports their time using the Timesheet function. This way we update the tasks and the actual costs for a project.
But sometimes the task in a project plan is not updated and the days for the task are different from the days the members are entering it in the timesheets. This could lead to small differences in "Actual Costs" if you create a financial report at the end of a month.
We need a financial report, where the "Actual Costs" of a project are based on the dates on the timesheets, but not on the dates of the tasks in a project plan.
One way to solve this would be to always have the tasks with the days uptodate. But this is not always achievable.
Has anyone an idea on how to solve this ?
Thanks