Hi all,
I have several questions.
1. Is it possible to somehow link the internal corporate sharepoint calendars with calendars in PWA?
2. If not, how you can display in PWA enterprise calendar (holidays) and resource calendar for each employee (vacation, sick leave).
3. I plan to create administrative tasks (vacation, training, business trip, sick), so that each employee can report back if he was ill, trained or was on vacation. I do not know how much it will be correct.
The goal - is to take into account resource availability on the chart, such training, travel, etc.
The manager, if he appointed a task order to an employee who, for example, at the hospital, just saw it and reassign it to another.