Admin tasks not appearing on timesheets in Project Server 2010

$
0
0

  I have Project Server 2010 with SP2.  For the last few weeks, the Admin tasks have not appeared on my timesheet.  I can manually add them via Add Line, but that must be done every week. If I manually create a new timesheet from Manage Timesheets I get the error message: "The timesheet creation failed, because of a problem with the project server or with data validations, such as resources or users.  Check your environment, and then try again."  The tiomesheet gets created w/o the Admin tasks.  If I try to delete a timesheet with missing tasks, I get a longer error reported in my Manage queues:

"General
Reporting message processor failed:
ReportingTimesheetDeleteMessageFailed (24011) - Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.. Details: id='24011' name='ReportingTimesheetDeleteMessageFailed' uid='41ac2c47-48ef-4e9e-bc0c-6450b8f4a77f' QueueMessageBody='TimesheetUid='c9b1688b-1050-4838-9115-1232de307b2b'' Error='Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.'.
ReportingTimesheetDeleteMessageFailed (24011) - Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.. Details: id='24011' name='ReportingTimesheetDeleteMessageFailed' uid='0d48246b-b1f0-4930-9165-90c316201f45' QueueMessageBody='TimesheetUid='c9b1688b-1050-4838-9115-1232de307b2b'' Error='Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.'.
ReportingTimesheetDeleteMessageFailed (24011) - Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.. Details: id='24011' name='ReportingTimesheetDeleteMessageFailed' uid='0c8bd480-46be-4e84-acfb-0f71dcc3d931' QueueMessageBody='TimesheetUid='c9b1688b-1050-4838-9115-1232de307b2b'' Error='Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.'.
ReportingTimesheetDeleteMessageFailed (24011) - Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.. Details: id='24011' name='ReportingTimesheetDeleteMessageFailed' uid='b18610d9-2f13-4161-b603-29044bf01ede' QueueMessageBody='TimesheetUid='c9b1688b-1050-4838-9115-1232de307b2b'' Error='Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.'.
ReportingTimesheetDeleteMessageFailed (24011) - Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.. Details: id='24011' name='ReportingTimesheetDeleteMessageFailed' uid='1c493108-e0a8-497c-9f3f-46bfef73a71d' QueueMessageBody='TimesheetUid='c9b1688b-1050-4838-9115-1232de307b2b'' Error='Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.'.
ReportingTimesheetDeleteMessageFailed (24011) - Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.. Details: id='24011' name='ReportingTimesheetDeleteMessageFailed' uid='733c03e7-cdb0-44ca-829a-28f243c49a98' QueueMessageBody='TimesheetUid='c9b1688b-1050-4838-9115-1232de307b2b'' Error='Invalid call to MSP_EpmDeleteTimesheetAdminAssignments. Timesheet UID (C9B1688B-1050-4838-9115-1232DE307B2B) was not found in MSP_Timesheet.'.
Queue:
GeneralQueueJobFailed (26000) - ReportingTimesheetDelete.ReportTimesheetDeleteMessageEx. Details: id='26000' name='GeneralQueueJobFailed' uid='01f17872-30eb-4a39-8524-6c82c03bb516' JobUID='c43c8670-670a-40a3-9102-73e1067295ad' ComputerName='ENGPROJECTSVR' GroupType='ReportingTimesheetDelete' MessageType='ReportTimesheetDeleteMessageEx' MessageId='1' Stage=''. For more details, check the ULS logs on machine ENGPROJECTSVR for entries with JobUID c43c8670-670a-40a3-9102-73e1067295ad. "  This seems to say the delete failed because it tried to delete the Admin tasks and they weren't there. 

Any suggestions?


Eric J Campbell


Can't delete a failed job/error detail

$
0
0

Hi,

I had a few jobs fail earlier, but succeeded later.

However the error messages remain in the "Manage Queue Jobs" page.

Even when I set the check boxes, the "Cancel Jobs" button is disabled.

How can I clear the list? Will this list grow infinitely (I hope not)?

Thank you, Caesar.


Thanks! Caesar.


How to install cumulative updates?

$
0
0

Hi,

I have SharePoint 2013 and Project Server 2013. 

For cumulative updates, I just have to apply PS2013's cumulative update right? Or do I need to install SP2013's as well?

What is the proper procedure to install the updates?

  • Do I need to shutdown services first?
  • What services?
  • In what order?
  • I'm assuming SQL Server is kept running.

Thank you, Caesar.


Thanks! Caesar.

How can I undo check-out for a project?

$
0
0

Hi,

There doesn't seem to be a way to revert a checked-out project (which has had changes made to it) to a state right before it was checked-out.

In other words I'd like to discard the check-out.

Is there a way to do that?

Thank you, Caesar.


Thanks! Caesar.

DNS

$
0
0

Hello

Scenario: 

2 Sites - 4 DC (2 DC in each Site) 

all DC gustavo.com

what i need : 2 DNS non recursive (will be my DNS out of the WORLD) 

                    2 DNS recursive from internal company but they need be hide from the world 

i know that the best option is add a linux DNS but is not possible, i need to do this with the 4 DC's

So, what is the best i can do...? thanks!

TFS - Project Server Integration: business process for remaining work

$
0
0

Hi,

we are running Project Server 2013 and TFS 2012 und the synchronization.

In TFS, the scrum template is used. In our mapping for Remaining Work, on conflict is set to PSWin.

For time tracking, we are using “Project Server My Tasks”. This is done via an automatic interface to our time tracking system.

In case that only Product Backlog Items are mapped (and not Tasks), we encounter the following problem:

The Project Manager inserts a Product Backlog Item in the Project Plan, assigns it to the Development Manager and sets Remaining Work to 60 hrs.

The Product Backlog Item is mapped to TFS.

The Development Manager splits the PBI into two tasks and sets Remaining Work to 40 hrs on each task.

80hrs are mapped back to the Project Plan as the (Remaining) Work or the PBI.

The Project Manager sets the baseline and the Development can start.

The Developer inserts Actual Work into “My Tasks”.

In the Project Plan, Actual Work, Work and Remaining Work are updated accordingly:

In the Project Backlog Item, Remaining Work is set to the correct value of 24 hours (Mapped Fields (Project Plan)).

But in the Task, the originally set remaining work is unchanged.

Thus the sum of Remaining Work on the Tasks differs from the Remaining Work on the PBI.

How can we solve this issue? Do we need changes in our business process or in the mapping? Any help is highly appreciated.

Regards

Sylvia


Documents linked to task won't show icon

$
0
0

Hello,

When linking documents to tasks as related items I notice that the icon won't show up in the Gantt view, however it does with issues and risk. Do you know why?

Thank you in advance


Project Web App Schedule dates do not match MS Project Dates - Pulling the start date of its predecessor

$
0
0
SandyStrong        asked on       <button aria-label="Date" class="msaActionText msgHistoryBtn info-panel-toggle-link" data-panelcontainer=".userInfo" data-paneltarget="#message-history-holder-4d97407a-eeda-4415-912d-060ca47a2b5d" title="See post history">September 30, 2015See post history</button>

I have some schedules that are pulling the start date of the preceeding activity.  Below are screen shots.

MS Project 2010 dates.

Image

PWA dates

Image

As you can see, PWA dates are pulling from its predecessor of Pre-Job meeting.  Logic is fs +15.  Pre-Job is As Late As Possible (which I believe is the issue).

I have 6000 schedules in the database and do not want to change the logic to fix what appears to be a possible bug?  I can fix it in PWA by saving and publishing the schedule in MSP and then going to PWA, but it reverts back overnight to the Pre-Job start date.  Any solutions would be greatly appreciated.


Collapsed Summary Tasks cannot be expanded after publish.

$
0
0

ProjectServer 2013 Feb 2015 CU (server and client both)

15.0.4693.1000 and 15.0.4701.1000 resp.

We've found and been able to reproduce the following issue:

  • Create a plan in Project Pro with a simple WBS containing a few summary tasks having one or several sub tasks each.
  • Collapse one or several of the summary tasks - rolling up the sub tasks.
  • Save and Publish and check in the plan.

Switch over to the web interface and look at the published plan - everything looks fine.

Open the plan for editing in the web interface.

Now all collapsed tasks are gone and the summary tasks cannot be expanded - indeed, there's not even an 'expand' arrow available and trying the Outline/Expand ribbon button doesn't help.

Our problem is that we have different people preparing the plans, using the full-blown client, and other doing simpler work using the web interface only. One particular step in the preparation of the plan is to perform a number of operations on summary tasks only, thus naturally using the collapsed tasks state for this work and then publishing directly after that.

Setting a SQL trace reveals that all the tasks are retrieved from the database, meaning that the issue is introduced on the application server side of things.

I would appreciate if anyone with a workaround - apart from "don't collapse tasks before publishing" - has anything to add.

/Lars Hammarberg


//Lars Hammarberg www.acando.se


Error Message

$
0
0

I am getting the following error message:  " Project Professional needs to be installed to open the project. Install Project and try again." However, Project Professional is installed. 

Workflow not found

$
0
0

I have Workflow Not Found error when I try to Access the page https://server:port/PWA/_layouts/15/wrkstat.aspx?WorkflowInstanceName={217fe4f5-1676-4774-a658-304cf677cb85}

Other projects work ok, only a few projects have this behaviour

We have March 10, 2015 cumulative update for Project Server 2013 (KB2956162) install

SharePoint Logs:

Application error when access /_layouts/15/wrkstat.aspx, Error=No encontramos el flujo de trabajo. 
 at Microsoft.SharePoint.WorkflowServices.ApplicationPages.WrkStatPage.OnLoad(EventArgs e)   
 at System.Web.UI.Control.LoadRecursive()   
 at System.Web.UI.Page.ProcessRequestMain(Boolean includeStagesBeforeAsyncPoint, Boolean includeStagesAfterAsyncPoint)
 
Microsoft.SharePoint.SPException: No encontramos el flujo de trabajo.  
 at Microsoft.SharePoint.WorkflowServices.ApplicationPages.WrkStatPage.OnLoad(EventArgs e)   
 at System.Web.UI.Control.LoadRecursive()   
 at System.Web.UI.Page.ProcessRequestMain(Boolean includeStagesBeforeAsyncPoint, Boolean includeStagesAfterAsyncPoint)
 
Getting Error Message for Exception System.Web.HttpUnhandledException (0x80004005): Exception of type 'System.Web.HttpUnhandledException' was thrown. ---> Microsoft.SharePoint.SPException: No encontramos el flujo de trabajo.   
 at Microsoft.SharePoint.WorkflowServices.ApplicationPages.WrkStatPage.OnLoad(EventArgs e)   
 at System.Web.UI.Control.LoadRecursive()   
 at System.Web.UI.Page.ProcessRequestMain(Boolean includeStagesBeforeAsyncPoint, Boolean includeStagesAfterAsyncPoint)   
 at System.Web.UI.Page.HandleError(Exception e)   
 at System.Web.UI.Page.ProcessRequestMain(Boolean includeStagesBeforeAsyncPoint, Boolean includeStagesAfterAsyncPoint)   
 at System.Web.UI.Page.ProcessRequest(Boolean includeStagesBeforeAsyncPoint, Boolean includeStagesAfterAsyncPoint)   
 at System.Web.UI.Page.ProcessRequest()   
 at System.Web.UI.Page.ProcessRequest(HttpContext context)   
 at System.Web.HttpApplication.CallHandlerExecutionStep.System.Web.HttpApplication.IExecutionStep.Execute()   
 at System.Web.HttpApplication.ExecuteStep(IExecutionStep step, Boolean& completedSynchronously)

Risk, Issues and Documents in SQL

$
0
0

Hello,

Can I query in SQL the names of the "related items" of a task? (Risk, Issues and Documents)

Thank you in advance.

Unable to save look up Table created in MSPS 2010

$
0
0

Hello,

I am unable to save the look up table created in msps 2010.

Code preview value has the value '*'

The values in the look up table are : HR; IT, FINANCE

While saving the look up table; the error message given is

"One or more code values in the lookup table either do not match the mask defined for the code or contain more than 255 characters.

Kindly help.

Soudha


Project Server and Project Pro 2013 - Tasks not allowing Uncomplete Work to be rescheduled

$
0
0

We are current;y running Project Server 2013 on Premise and using timesheets to update task status. We are using the proactive task scheduling to let the allocations, work and dependencies drive the schedule to get accurate project finish dates.

We have several projects that give an error stating "Change would modify work entered by a team member" and "We can't make that change because Project Web App is set to only allow actual work to be entered by a team member through Timesheets or My Work" when setting the status date and Updating the Project and selecting reschedule Uncompleted Work to start after the status date. We have determined that usually it is only a single task causing the error. we have tried to remove the resource when no actuals have been entered but we get the same issue. Any help would be greatly appreciated.

how to create PWA site under new different site collection on port 80

$
0
0

Hi All,

I have a PWA site created on Port 80 but i some how lost permission to access PWA site. My manager asked me to have another PWA site under different site collection on port 80.

Can some one please guide me here?


MercuryMan


New MS Project Does Not Match Project Server 2010 PWA Page

$
0
0

Hello All,

One of my PMs created a new project, but the project in MS Project did not match the project in Project Server 2010, specifically the Work, Start/Finish Dates, and Remaining Work hours.  [We need to back-out hours charged to an existing project from last week and apply them to this project.]  I couldn't figure out the problem, so I re-created the project using File/Save As and over-wrote the new project my PM created.  I deleted everything in the file and re-created the tasks, assigned the Resources, Saved, Baselined, and Published the project.  Now the Start/Finish dates in the MS Project match the Project Center data on the PWA Page, but the Work and Remaining Work hours do not match. 

I deleted the new project, including the Project Site.  I started from our template and created a whole new project with a slightly different file name.  Same problem, Work and Remaining work do not match between MS Project and PWA.  I moved the hours from the existing project and put them on the new project, and now even the Actual Work hours do not match.  

Any ideas what is causing this mismatch?

Julie

Project Site Template - PS 2013

$
0
0

Hello All,

Environment : Project Server 2013

Wanted to configure all the Risks and Issues to open in a Dialog Box. Managed to enable the same in the Advanced Settings (Launch forms in a dialog).

But when i save the same site as a template, the Dialog box setting is being reverted back to No and the Risks and Issues for any new project created are opening in a full page.

Any thoughts on this !!

Regards, Dan

How do I change the owner of the Active Directory Resource Pool Synchronization automated job?

$
0
0

Project Server 2010

The current owner of the Active Directory Resource Pool Synchronization job is no longer active in Project Server which has caused some issues. I am the new Admin over the system and thought if I ran the job manually it would reassign the ownership of the task to me. Since the job runs under the credentials of the owner, we're getting some errors.

Let me know if any more information would be helpful!

Thank you

Timesheet view Failure for some resources

$
0
0

Recently we are having some problem with timesheet view failure happening for a no. of resources.

The logs shoot the following error:

Error is: GeneralUnhandledException. Details: General Unhandled Exception in _TimeSheet.GetTimesheetForGridJsonFromViewUid_ Attributes:  System.InvalidOperationException: GetDataForAssignment: Did not find data for assignment. ProjUid=************* AssnUid=*******************

In some cases, republishing the Project resolves the issues but this is happening over and again.

Any help greatly appreciated.

PWA provision failed in project server 2013

$
0
0
Failed to provision site PWA with error: System.ServiceModel.ServerTooBusyException: The HTTP service located at http://ktnapapp315:32843/0a87ee24145443f982368b061d87d6cc/PSI/psiserviceapp.svc is unavailable.  This could be because the service is too busy or because no endpoint was found listening at the specified address. Please ensure that the address is correct and try accessing the service again later. ---> System.Net.WebException: The remote server returned an error: (503) Server Unavailable.
   at System.Net.HttpWebRequest.GetResponse()
   at System.ServiceModel.Channels.HttpChannelFactory`1.HttpRequestChannel.HttpChannelRequest.WaitForReply(TimeSpan timeout)