When changing remaining work to "0 hrs" to the task, the task is become...
Hi,Have created one task in the project plan from 5th to 10th(6 days - Work(48 hrs)).Later thought that, this task we have not done any work as this task cancelled.In this scenario, if i go and change...
View ArticleConnecting Primavera client to MS Project Server 2013
HiI work with Engineers who uses Primavera to build their plansThere is a chance to implement Microsoft Project Server, only if it supports Primavera?I did some search and found it doesn't do thatI do...
View ArticleSchedule variance for the whole project
Hello all,We are using PS 2007 SP2.we want to view the schedule variance for the whole project (i.e. the sum of schedule variance field for all tasks i have in a project) in both MS Project...
View ArticleHow to calculate ACWP, BCWP,BCWS, SPI , CPI values and baseline the project ?
Hi ,We have baselined our project but still the values are showing to be zero for all these fields.Can anybody put some light on what are the necessary fields that are required in order for these...
View ArticleTask reminder emails for Project Server 2013 have subject line "Task...
Hello,I have a couple environments in which I upgraded Project Server 2010 to 2013 via DB attach. I only recently noticed that when Task Reminders are sent out, the subject line contains "Task...
View ArticleCustom Text Field used in IIF Formula not working
I feel I ought to know how to do this; but it's not working and my mind elsewhere than debugging Project ....I have a Custom Text [Text21] field renamed "Milestone Level" with three lookup values: "MS...
View ArticleManaging Projects in PWA
In order to edit projects in PWA is the user required to have MS Project Professional installed on their computer?
View ArticleProject Information Disappeared in Project Details Page
Hi,On Project Server 2010.Clicking on Project Name in Project Centre takes me to the Project Detail page as normal. Of the 2 options in menu on left, Schedule and Project Information, Schedule is fine...
View ArticleProject Server 2013 - Tasks list in SharePoint is inaccessible
We're seeing an issue in Project Server 2013 where we have a Project site (in SP2013) for a project originally created using Project Professional 2013. Everything about the site appears to work...
View ArticleProject Server 2010 compatibility with IE11 and Windows 8.1
Hi All!Maybe a silly question since compatibility is always asked about older versions, but here is my question:Is Project Server 2010 compatible with IE11 and Windows 8.1?I personnaly tested with IE11...
View ArticleNeed help configuring Excel Services
I've configured both the Excel Serives and Secure Store Target applications and continually receive the following error message when trying to view the Simple Projects List sample report:An error...
View ArticleIssue with IE 10
Hi I am using Project server 2010 and IE version 10. When ever i click any link from quick launch menu ( Project center , server settings) getting error "This Web Part Requires at least Microsoft...
View ArticleUnable to save/publish Projects on Project Server 2010() using Project Pro...
Hi,Recently we have upgraded from Project Server 2007 to 2010 SP-2 (BCM enabled) environment and from last few days we are getting issue with Project Plans where PMs are not able to update Projects...
View Articlehow to simulate %complete by custom fields in project server 2010
Hi every one,how can I simulate %complete in project server 2010 by custom fields?I built some custome fields and simulate it but I have problem in task with split. how can I fix it?it seems project...
View Articlehow to change status date for all project in pwa
Hi every one;is there any way to update status date for all project without opening all projects and set status date one by one then save&publish them?our client have about 300 project(small and...
View Articlegetting access denied when trying to change or update the profile in PWA
It’s a strange behavior observed for users belonging to project managers group or admin group in PWA...We have a Project server 2010 installed with SP2.I am the member of the admin group in PWA. Was...
View ArticleShould Project Server be on it's own server?
We're looking at implementing Project Server 2013. Should it be on it's own server, or can it be on our existing intranet server (and using our database server for it's data)? I suppose I'd be ok...
View ArticleECF not visible to other resources
I'd like my resources to pass comments to resources working on dependent tasks. I've created several Task-level ECFs called Type, Quantity, Comments (examples). When one resource fills in the details...
View ArticleAre you sure you want to navigate away from this page?
Hi All,When user enters/modify text in a rich text field, saves successfully, then tries to navigate to another page, a pop-up box appears which says there are unsaved changes on the page and "Are you...
View ArticleUser is not getting added in "Project Server view Olap Data role"
Hi EveryoneThere is one user "User1" in pwa site who belongs to "Project manager" group,This group is having permision "View Olap data",all the users in this group are able to viewolap reports except...
View Article