How to add Baseline Work [Assignment] field on Timesheet View
I want to creating a Timesheet View on Project server 2010. I follow the following steps.Server Settings > Look and Feel > Manage View > New ViewI select View Type: TimesheetOn Available...
View ArticleGetting error while publishing the new Plan in Project server 2013
Dear Team , Please help me below errorQueue:GeneralQueueJobFailed (26000) - CreateWssSite.CreateWssSiteMessage. Details: id='26000' name='GeneralQueueJobFailed'...
View ArticleResource Availible % and Task work %
All,I am somewhat confused about how the cost for a resource assigned to a task is calculated. Something seems counter intuitive to me on this. Here is the example situationI have three...
View ArticleAssignment Owner in PWA 2013
I have had a brief search for an answer to this question both on the Web as a whole and in this Forum without success.In previous versions of Project Server an assigned resource tended to be the...
View ArticleTraffic Light at the Project Center Level
Hi all,I am currently using a customized traffic light field in MS Project 2010 and MS Project Server 2010. Currently the field is only visible in the project's timeline level. To see the overall...
View ArticleCorrupted Project in 2010
I have an ongoing issue with a corrupted project1) the project manager can no longer get to the Approval Center (he gets an access denied message).2) Project will not publish. 23000 Error below<?xml...
View ArticleFailed to provision site pwa with error
I have a user that is going into Microsoft Project Professional. Trying to go into resource, resource pool, and enterprise resource pool is grayed out. After researching I found that I have to go into...
View ArticleProject Hosted - How to
Can someone let me know if there is any documentation on how to implement a hosted version of Project for a Private Cloud?I do know there are partners who offer this as a service but a particular...
View ArticleHow to change Project Server Workflow Proxy User Account (while having...
I used to have account1 as a Workflow Proxy Account and I have around 400 Project instance with 3 different EPTs on my server, I changed it to account2, both accounts has all the Global Permissions and...
View ArticleBest practices for changing resource's calendars
Hi!I would like to know the recommended way for changing a resource's calendar. The issue is:We open the Resource Center in Project ProfessionalWe then change the resource's calendar using the button...
View ArticleAn unknown error occured issue in Microsoft project server 2010
Hi,I have got an issue in microsoft project server.users are not able to access task tab under my work. They are getting error "an unknown error occured".Could you please help to give some solutions...
View ArticleHow to link an Excel cell to a Project Server Custom Field
Hi,I'm using Project Server 2010, and I would like to link an Excel cell to a Project Server Custom Field. I've installed the PS 2010 Solution Starters Excel Project Cost Capture, and I have followed...
View ArticleProject Server 2010 with SSRS 2012 ?
I have posted this question in Administration Forum as well but not getting any response there so posting here again, hoping some one will share thoughts on this.Question : We have project server 2010...
View ArticleActive Directory Enterprise Resource Pool Synchronization
I'm running in to an issue with Project Server 2013 that has me pulling my hair out. A co-worker and I switched it over from SharePoint Permissions Mode to Project Permissions Mode and are trying to...
View ArticleProject Server 2013: View, Edit, Delete options missing from PWA site menu
Hi,Installed Project Server 2013 on Sharepoint Enterprise 2013 and Windows Server 2012 Standard Evaluation.After creating a PWA site and pulling out its menu, I see this: http://imgur.com/LwbuXHCI...
View ArticlePWA OLAP Extract into Excel?
I have a OLAP pivot table filtered by project name looking like this that I can pull information from, but the values change when I filter by another project. Addressing the cell with the 59.5 vbalue...
View ArticleSharepoint 2013 and Project Server 2013 error
Hi All, We are using SharePoint 2013 and Project Server 2013. When we click on the project center and then on the project name to view more detailsEven we click on a document lib to view documents...
View ArticleEfficiently Updating Resource Cost Rate Tables
Hi gang,Is it possible in version (server) 2010 to update resources' cost rates tables in bulk? I.e., we would like edit the resource profile for a set of resources... e.g., edit table A, B, and C...
View ArticleCustomizing Cube Reports Project Server 2013
I am fairly new to Project Server and I have been tasked with implementing Project Server 2013 into an enterprise environment. We are currently on Project Server 2003, and I am having a hard time...
View ArticleMS Project Server 2010 - Resource Availability and Resource Assignment Views...
We are using Project Server 2010 and set up for single mode entry on the PWA timesheet. Resources enter their actual work per day per task and enter their remaining work and then "Send Status" every...
View Article