When changing remaining work to "0 hrs" to the task, the task is become Milestone. How to prevent this?

$
0
0

Hi,

Have created one task in the project plan from 5th to 10th(6 days - Work(48 hrs)).

Later thought that, this task we have not done any work as this task cancelled.

In this scenario, if i go and change the remaining work to "0 hrs" for the task then task is changing Milestone from 
"No" to "Yes". but actually this task is not a milestone task.

How to prevent this without changing the Milestone?

Could anyone please help me on this?

Many thanks in advance.

Thanks

Venkat.