Hi,
Have created one task in the project plan from 5th to 10th(6 days - Work(48 hrs)).
Later thought that, this task we have not done any work as this task cancelled.
In this scenario, if i go and change the remaining work to "0 hrs" for the task then task is changing Milestone from
"No" to "Yes". but actually this task is not a milestone task.
How to prevent this without changing the Milestone?
Could anyone please help me on this?
Many thanks in advance.
Thanks
Venkat.