I have posted the time through timesheet (8 hrs) in Task A and Actual Start of Task A has been stamped with 10-Apr-2010 and Actual work is update to 8 hrs from zero and % complete to 20% from zero.
After timesheet has been approved it has been notice that time has been logged in Task A instead of Task B. Now i want to recall the updated Task A, i.e, Actual work should has to update to zero from 8 hrs and % complete to zero instead of 20% and Actual Start should be clear, so that i can enter the Hours in Task B.
Please note: Actuals has been locked, task update is protected, user can logged the time through timesheet only. Its Single Entry mode.
How we can reset the Task to not started(% compelte to zero and actual work to 0)
Farhan
farhan