How to clear the Actual start date and mark actual work to 0 & %compete to 0
I have posted the time through timesheet (8 hrs) in Task A and Actual Start of Task A has been stamped with 10-Apr-2010 and Actual work is update to 8 hrs from zero and % complete to 20% from...
View Articleunscheduled task appearing in timesheet
Some of the task which is not in the schedule date(start & finish date not within timesheet reporting period) are also appearing in the user timsheet. In the timesheet only those task should...
View ArticleLogs to check when a particluar project was published
Is there a way where i can check when a particular project was published? There is a field called last published date, but i also want to see how many times and when this project was published before...
View ArticleAdministrative tasks start and finish
Hi ! Can I enter start and finish dates with time for administrative tasks? These fields r greyed out now. Thanks in advance. Regards Palani
View ArticleSave Hours on Task
dears,if task has saved and submitted hours for a given duration such as:task x has 32 submitted hours from 1-4-2013 to 4-4-2013 and also has 32saved(not submitted) hours from 5-4-2013 to 7-4-2013.i...
View ArticleCustom risk category and issues category
Hi, I want to replace the default risk categories list item with my own list of values. Similarly for issues catrgory list as well. These new categories lists should be automatically attached to my...
View ArticleAdd custom field with resource (AD users) look up to PWA project
Hello,I would like to add a custom field to PWA projects in which I should be able to browse the sync'ed AD users/ resources. For eg. like owner property of the project.Thanks for the reply.
View ArticleProblem when exporting from Project 2010 SP1 to XML probably caused by a KB
Hello,On all our Windows 7 SP1 64 bits machines, with Project 2010 SP1 32 bits, it was possible to export a project to XML without any issue (the file created really had an XML structure), until I...
View ArticleTask Updates from Timesheets are Appearing in Wrong Week
Hi,We are using Project Server 2010 with weekly Timesheet entry in Single Entry Mode. We are up to date on all service packs. A resource completed his timesheet and entered 8 hours for a task for...
View ArticleProject Server 2010 - Users Modifying Fields within MS Project appears to...
Hello everyone. It’s been some time, but I’ve got another situation that I’d love to hear everyone's feedback on.A very unusual issue has surfaced surrounding users and their personal modifications of...
View ArticleI have problem with EV (BCWP)
I have problem with EV (BCWP) in my project.I set in the MSP 2010thepropertieson theAdvancedtabin the“Baseline for Earned Value calculation” - Baseline3. In theTaskUsageview,everything is OKandthe...
View ArticleCreate cross project links on Ms project 2010
I would like to link some tasks between two different project and I do not have Ms Project server. I used to do it on Ms Project 2007.
View ArticleCost Resources
We want to introduce the use of Cost Resources in MS Project Server 2010 and would like to enter in Cost and Actual Cost information at a monthly level. One resource we’ve consistently used tells us...
View ArticleRecalled Timesheets Difference
Initial Problem: We were told by resources that hours were disappearing from people’s timesheets. Findings: We found out that a scheduler was taking projects off line to work on them at different...
View ArticleResource Plan Date Range changes re-allocate spread of the forecasts
MSProject 2010 Enterprise, June 2012 CU.We are using Resource Plans extensively. Some plans are administered by multiple users. We have found that changing the Date Range settings and then saving the...
View ArticleTask updates moving start date before the true start date adding 0 actual...
We are using Project Server 2010, Windows 8 and SQL 2008 R2.This is a bug and I need to find out if Microsoft has a fix for this bug. My support vendor validated that this is a bug and was able to...
View Article74-343 and 74-344 Project Server 2013 exams
Hello all, I would like to find people who have written any of these new Project Server exams. Please kindly reply this post.Thanks.
View ArticleProject Server 2010 Schedule Printing Issues with IE10
We are currently running Project Server 2010 (December 2011 CU). Some of our users have been upgraded to IE 10. Having them utilize PWA while in compatibility mode seems to generally work, except for...
View ArticleWhenever I submit the submit the timesheet this message occurs –
Whenever I submit the submit the timesheet this message occurs – Please do not use the remove task function. This removes your assignment from the task and is non-recoverable. Talk to your project...
View ArticleDepartment Head needs to be able to update multiple plans
I have a department head who needs to be able to update multiple project plans. These plans will be authored by him and updated by him. The plans contain assignments to named resources in his team. In...
View Article