Hello
I am looking into using MS Project with Project server for a project with over 200 procurement packages, in different type and size. All packages contain relationships outside of their package. I have a few questions:
Is it recommended to set up a project like this in sub-projects with a master schedule that collects the over 200 sub-projects?
Is it possible and similar work to track the logic between 200 sub-projects in a master schedule vs. one large project schedule?
Could I use grouping in the master schedule?
Could I use a Go-to function in the master schedule?