Hello All,
I have a couple of questions just to be sure that I am using PWA correctly. I am using SharePoint task list projects. I am new to PWA and I have really searched a lot.
1) When i create SharePoint task list project, tasks and assign these tasks to resources, project will appear in project center to resources but will give access denied if clicked (if they weren't explicitly granted access on it). I mean permissions will not be granted automatically. Same goes for portfolio managers and viewers.
2) While assigning tasks, all active directory users will appear not the resources defined in the Active Directory Resource pool synchronization group.
3) How can i give permission on PWA to active directory group. that whenever any resource is added in active directory group, it is granted team member permission on PWA
4) how can I set baseline for SharePoint task list projects? Is it only available to enterprise projects?
5) why is the project percentage of completion always set to 0 even if it contains only one task that is partially completed (70% done for example)