Quantcast
Channel: Project Server General Questions and Answers forum
Browsing all 7942 articles
Browse latest View live

Migration leading to Duplicate Resources

I am facing enormous issues while migrating plans created in msps 2007 to msps 2010.I am having duplicate resources while migrating plans from msps 2007 to msps 2010 and actuals are not reallocated to...

View Article


Load Summary Resource Assignments is Unchecked but the Other Projects &...

So this is really cooking my noodle...I just deployed Project Server 2010 to my organization.  Testing was fine (as fine as any deployment can go) but now the really mean gremlins have come out.  One...

View Article


Generate New Project Number Help

User Need Our company uses Project Server and Project Web App, but we need help with project numbers. We want to generate a project number whenever a project is created. We also need to display the...

View Article

Queue Job Failure Alerts to SysAdmins

What is the simplest way to have a systems admin group notified when Queued Jobs fail in Project Server 2010?

View Article

Progress Bar - Gantt chart

Hi, Just that the plan needs to be sent to customer. I have created a slave plan. From the original plan i have picked up START,FINISH,TASK_LEVEL_FIELD  (for this field a value between 1-100 is entered...

View Article


Import 100 Project Plans Project Server 2013

Does anyone have the ability or capability to import project plans into Project Server 2013, I have attempted to use the old solutions Bulk Import but it does not seem to work. I also wanted to try to...

View Article

Display custom field value when reassign task

I've created new task and inserted values for custom fields and reassigned this task to another resource but that custom fields display nothing (empty). Can anyone help ?

View Article

Manage Queue page is timing out after restoring farm in Project Server 2007

I am using Project Server 2007 sp3 with SharePoint 2007 sp3 and SQl Server 2008r2.I have recently restored a farm that has three PWA instances to another environment. Two of them are working fine. In...

View Article


Project Server 2010 Document Library MS Word Master Documents

Hi all Project Server 2010 SP1 all CU are up to date.  Regarding 1 of our documet libraries, contains about 100 Word Documents around 5mb each.  a OM asked a user to create a Master Document that...

View Article


Duplicate Resources when migrating plans from msp 2007 to msp 2010

​Hello All,While migrating plans from msp 2007 to msp 2010. I am having duplicate resources in resource view. The resources were created using local account (GDNEUROPE) in msp 2007 while in msp2010 ,...

View Article

"An internal error occured. If the problem persists, contact your...

hi,often I have the following fenomenon.We work with MS Project 2010 and Enterprise project server 2010When I try to save my project file, I get the error shown in the title of this thread. No...

View Article

MS Project Server 2010 - Un able to assign remaining work to different...

Hi. I have a resourced task with Res-A. Res-A goes on leave (Adjust the resource calendar, record period away etc etc). In the Resource Usage view Res A's avaibility is greyed out while he is away - as...

View Article

Has Anyone Done Any Comparison with SAP PS vs. MS Project 2010?

Hi All,I look forward to your thoughts on this topic.Regards,Jeffrey

View Article


formulas don't calculate in project server 2010

Hi,I had 3 simple custom fieldsABC=A+Bwhen I use web application to enter data, the formula for column C doesn't workI have to do these steps to see calculated data in column C after entering data in...

View Article

When I amend an Enterprise Resource record and save changes, the record...

I have full administrative rights to Project Server 2010 and when I attempt to amend a user account, when I save the changes it appears as though it has changed successfully, however if I try to amend...

View Article


Project Server 2010 add time dimesion in built in cube

We would like to add time dimension based on a date custom date field to the built in cube MSP_Project_Sharepoint, so that user can select report for a particular period At present, it does not have...

View Article

Project Centre view - rollup of milestones?

Is it possible to roll up milestones to show on the project summary bar in a PWA Project Centre View?  Using PS2010

View Article


Archiving Projects

I have archived a project using the recommended method on office.com support- Marking tasks not to publish.  I no longer see the projects on project site as I changed the view to only active projects....

View Article

Reporting Services - Permissions question

Hi I have users who can access the BI centre, view reports in the library but they dont have the "Open in Excel" button when trying to down load a report from the Library.They are added into the Report...

View Article

Master project with subprojects and interaction with PWA

We have a large project that we need to break into sub projects and have those under a Master Project.  We are new to Project Server 2010 and Project Professional 2010.  My questions are...1.  I assume...

View Article
Browsing all 7942 articles
Browse latest View live


<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>