Add custom field with resource (AD users) look up to PWA project
Hello,I would like to add a custom field to PWA projects in which I should be able to browse the sync'ed AD users/ resources. For eg. like owner property of the project.Thanks for the reply.
View Article2013: cannot delete PWA instance from CA - is it bug or feature?
There is no menu "Delete" in the list of PWA webs or I don't see it? Try on RTM version, did not pay attention on Beta at this point. CA -> Application-Services mamagement -> Project Server - PWA...
View ArticleWhat is the difference between Project Shedule task and Project site Task in...
Hi,What is the difference between Project Shedule task and Project site Task in project server 2010 ?
View ArticleWhat is the Task Calendar ? What is the role of task calendar?
Hi,can someone tell me.What is the Task Calendar ? What is the role of task calendar in project server 2010?
View ArticleManage Users --Cannot Save, getting error "The resource could not be...
In Project Server 2010, in Server Settings > Manage Users we can't edit any existing users - no matter if we change something or not, as soon as we hit the SAVE-Button, we get this error: The...
View ArticleBranding With Project Site in Project Server 2010.
Hi,I want to do branding with Project Site in project server 2010.How can I accomplish this task ??
View ArticleReporting (Timesheet Project Aggregation) tasks "waiting to be processed"...
Project Server 2010 /SP2/SEMA few days ago, a job of the type Reporting (Timesheet Project Aggregation) in the queue got "stuck" (by which I mean it shows processing but at 0%) and some, but not all,...
View ArticleWorkflow function in Sharepoint/Project Enterprise 2010
Hi,Can someone send me a link or explain what is Workflow function in Sharepoint/Project Enterprise 2010?
View Articlequery optimizer techniques for sql server
Hi i am Nimra Memon MS(IT) student my research topic is Tool supported analysis of query processing and query optimization . i am going to implement various optimizer strategies for example...
View Articleactive issues and risk count is not coming
Hi all,i am attaching issues and risks at project level and task level. But i m not getting the count in active risk and issues column.help me outThank you
View ArticleTimephased grid is not displayed in Approval Center
Dear All,We are using Project Server 2010 SEM. One of our resource is not able to view the timephased grid in the Approval center to check the daywise entries. Below is the screenshot for the sameOnly...
View ArticleError Message when opening Project Plan on Project Professional from PWA 2013...
Dears,,One of our clients uses Google Chromeas their standard navigator to open PWA 2013 that we have deployed for them.Every thing went fine until we tried to open a project plan using Project...
View ArticleMS Project Server 2010: can server admins see all pending approvals?
Hello,is it possible that the project server administrator can see all pending approvals of all projects?In our organisation are not only team members which don't book their worked hours on projects....
View ArticlePWA 2013 Default Task Settings
We are using Project Server 2013. We have some projects that are created and managed using just the PWA web client only. When a new task is added to the schedule it defaults to Fixed Units Non Effort...
View ArticleProject Server / Project Pro => Cut and Paste official best practices to...
It is pretty common knowledge among Project Server veterans that Cut and Paste between Project Pro files can cause corruption with the assignment table. This leads to Publish and Reporting...
View ArticleTeam members don't see their tasks in EPM and the EPM manager in Resource Center
Hello,the project plan is published.The "Publish" column contains "Yes".The tasks contain few Resource Names.The Resources are defined at the higher tasks. I.e. Task 1.1. "Project Management" contains...
View ArticleHow to start ?
Hello All,I am working in SharePoint for last four year but I need to take up a Microsoft EPM (Project server 2013) project. I don't know from where should I start. I need to learn the development in...
View ArticleProject Server 2010 Approval Centre
Hi - We have a requirement in Microsoft Project Server 2010. Where in we mange N number of work plans assigned to Many work plan owners. The challenge we facing here is we need to know the last...
View ArticleTimesheet Failed to Load - Node Consistency Error
We are running a new Project Server 2013 with the December 2013 CU. Some users are getting "the view failed to load" error on timesheets if their assignment has been deleted in the plan.We are aware of...
View Article2010 - Cannot Change Enterprise Base Calendar for any resource
Hi I am having a problem with Enterprise Base Calendars,If I change a resource's base calendar from PWA I can save the page Ok but when I go back to the page/resource the calendar has not been...
View Article