Locked feature not working in PWA 2013
LSWhen I set tasks to 'Locked' in the browser and publish, check-in and then chek out again, the "locked" column is set to No again.How can I fix it?Texas Tonie
View ArticleHours showing up in TimeSheet for every day instead of a week
I am in Ms Project 2007. I have assigned 10 hours for a task from 2/3 to 2/7. In time sheet it shows as 2.5 hours per day. This forces me to enter 2.5 hours per day. Instead, i do not want PWA to...
View ArticleMicrosoft Project Professional and multimonitor for same project
Hi,I do have Windows 8.1 with Project Professional 2013. I have 3 monitors and my desktop is extended.I have one .mpp project file which is on Project Server 2013.I want to open Project application on...
View ArticleUI setting in 3D Builder App
Is it possible to add more options in more setting area or customize standered options in 3D builder application..??
View ArticleMissing Assembly Project Server 2013
Hi,I have a problem concerning the MS Project Server 2013.My Software:- I have a Windows Server 2012 on a VM (complete new not many changes in configuration)- A SharePoint Server 2013 (StandAlone)- A...
View ArticleProject Server 2013: View, Edit, Delete options missing from PWA site menu
Hi,Installed Project Server 2013 on Sharepoint Enterprise 2013 and Windows Server 2012 Standard Evaluation.After creating a PWA site and pulling out its menu, I see this: http://imgur.com/LwbuXHCI...
View ArticleEven if we uncheck “Load Summary Resource Assignments” box while opening the...
Reason/Issue: Even if we uncheck “Load Summary Resource Assignments” box while opening the plan it still does all those things which it is supposed to do only and only when it is selected. Which...
View ArticleTime and Date
Hi,I am using Project Serve 2013. I would like to display Time and Date for Start and End dates on each task. Swithc on/off by project.I know there is a "Time with Date" check box under "options on the...
View ArticleTimesheet Issues in PWA 2010
My company just upgraded from Project 2003 to Project 2010. In PWA 2003 timesheet view, we were able to see our summary tasks, as well as the Task IDs. I cannot find a way to display either in PWA...
View ArticleProject Server 2010 & Visio Services on SharePoint
Hello,I have been using Visio Services linked to SharePoint lists, but I understand I should be able to use data from Project Server (via the ODC?) in the same way.I can access Excel reports from...
View ArticleEnd date different in timesheet from plan
Hello All,We have a work plan that has fixed duration tasks that run from 11/18/2013 to 12/20/2013. The task is assigned to several resources and the planned work looks fine in the work plan. However,...
View ArticleProblem with Task Aggregation from Project Server with old Project Server...
Hi, I have installed Sharepoint 2013 with all CU, and Project Server 2013 with June CU update. Later, I attached database from old Project Server 2010 database, all was OK, but now I have my PWA with...
View ArticleTasks were deleted/moved by Project Managers after Time was reported by...
So here is the most bafling situation I have at hands. We are running MS Project Server 2010. There are many projects where users are assigned and time is being reported. Few of the PMs managed to...
View ArticleBulk Update Project Sites (PS2010) Not Working
Hey folks, I've a problem where I click on an Issue of a Project, and I get the dreaded "File Not Found" SP/PS error. Per documentation, running the Bulk Update Project Sites tool should resolve the...
View ArticleLoad a page with central project web part in a specific view
Alexandre Paiva, PMP, MCTS, ITIL Project Manager +55 (21) 8887-3645 alexandre.paiva@gerentedeprojeto.net.br www.gerentedeprojeto.net.br
View ArticleWeek number divided between months
Dear all,All our reports and calculations are week based. But in the OLAP cube derived from project server you can unfold the time field until week, but some weeks fall in two separate months. This...
View Articlelosing flag settings
I am using Project Server V2010 SP1. I updated a schedule on the Server via my laptop. In addition to making some date changes, I made some changes to a user defined flag that drives a filtered view....
View ArticleBaseline work by resource in database
Hi,We are not able to find baseline work by resource in Reporting database. Any ideas?We need to calculate work variance by resource, not by project or task.Thanks in advance!
View ArticleHours entered by delegate in time sheet not reflecting in reports
This is for Project Server 2013. Even I have faced this issues in PS 2010 and it still continues. There are 2 users. user A and user B. User A is on leave and User B has been set up as a delegate to...
View ArticleApprovals on Project Server 2013 - An unknown error has occurred
Migrated Project server 2010 to Project server 2013. All the quick launch pages were working after I completed the migration. Started the process of publishing projects and statusing/timesheets to...
View Article