Hours entered by delegate in time sheet not available in reporting
Here is the scenario. Project Server 2010. I set up a delegate to A for resoruce B as B is on leave. A acts as delegate and fills in timesheets for B for last 2 weeks and submits. Data entered in time...
View ArticleProject 2010 Tasks getting re-ordered/corrupted
We are using Project Professional and Project Server 2010. We've seen the following behavior a couple of times, with different users.We create a project and populate with tasks. We save the project...
View ArticlePWA 2013, team member viewing project schedule, "access denied" in the middle...
Hello everyone,we're seeing the following phenomenon in Project Server 2013:A team member (PWA group) logs onto PWA, goes to project center and clicks a project.The project schedule and timeline are...
View ArticleProject Server 2013 Workflow Submit Button Greyed Out
Hi I am trying to build a workflow for demand management, using SPD 2013.The workflow is a simple 3 stage affair.It seems to publish ok, I applied it to the EPT ok, can create a project ok, but cannot...
View Articleproject web access not showing all the tasks
Hi,We are using Project Server 2003. I have assigned few tasks to one of my resources. When I login to PWA and adjust actual work hours I don't see all of the tasks for this particular resource, but I...
View ArticleSaving from Project Professional to Project Server Gets stuck at around 90%...
Hi,We are getting an issue with save times from Project Professional to project server where the save is quick through to around 90% and then takes siginificant time to actually complete - up to 10...
View ArticleProject task email notification per project
Hi ,We need to setup automatic email reminder to project manager on delayed projects.How can set these type of scenario in project server 2010.Please share some knowledge on this.Thanks and...
View Article“Project Workflow Check-in” job got stuck in the queue
Dears,We have done a project server 2010 implementation with a custom workflow, in the workflow, we have created a custom activity to check-in the project when needed, the custom activity calls...
View Articlebalancing managing the project with tracking actuals
Has anyone developed or found a best practice for balancing the tracking of actual work with the managing of the project? It comes down to how one builds the schedule and the methodology they use to...
View ArticleSecure a Project Based off of Custom Field?
Forgive my question, but I am a project server newbie. My security requirements are as follows.The entire organization can view (most) all projects. However, certain projects need to be marked as...
View ArticleProject Server 2013 - Cannot change project owner
Hi,I am having difficulty changing the project owner for a particular project. Full permissions have been granted to the new project owner on the project. When I change to the new owner in the project...
View ArticleCustom Field with value, but not entered
We have a custom field that gets a value of "201306-000450", but there is no event handlers on the server that sets the value and even if not entered when creating a project the value is still...
View ArticleSyncing a project site with a new schedule
I understand from another forum post (http://social.technet.microsoft.com/Forums/projectserver/en-US/17137381-28d4-4610-8c6d-ba8fdda0b118/multiple-project-schedules-linked-to-one-project-site) that one...
View ArticleInternet Explorer 8 issue in project server 2007
Hi,When i click on New user(manage users - New user) button in PWA it is not opening, nothing appears.I am using IE8, i tried using compatibility view. It doesn't work.Please help.K.Gokulraj
View ArticleStatus error while submitting timesheets
I have come across this issue umpteen number of times. My colleagues often see this error. What happens is, whenever they submit their timesheet, it shows a red color strip, on that strip there is some...
View ArticleIs it possible to edit each resouce's actual work using PWA or CSOM in...
Hi, in our project, each task can be assigned to multiple people. So we need every person to report his/her own actual work hours. Is this possible?I noticed in PWA, I can modify the whole task's...
View ArticleProject 2010 multiple task dependencies
Let's say I have 3 tasks, 1, 2 and 3. I'm trying to make task 3 start when task 1 starts and end when task 2 ends. Help?
View ArticleChange Status Manager on Project Server 2010
Dear all,I have a question regarding chnaging Status Manager on Project Server 2010.Scenario is the following:1. A user from PMO creates the Project from his account on EPM 2010 (Web) > save >...
View ArticleTimesheet doesn't sent to Approver
Hi all,We are working on Project Server 2010. When users send Timesheets, some timesheets don't send to the Approver. If the user acceses to Manage Timesheets the column "Next Approver" is blank for...
View ArticleCompleted tasks no longer complete in Project Server
I have a schedule in Project Server 2010, and there are about 5 tasks that keep losing their % complete.They are marked as 100% complete with finish dates in the past, I publish the schedule to Project...
View Article