Hi,
We are on Project Server 2010 with August 2012 CU. We take a report on Actual Hours from MSP_EPMAssignmentByDay table.
One of our projects, which used to show a total of around 2000 hours, is now showing 0 hours in the report.
On further analysis, it was observed that the table MSP_TimesheetActual has all the actual hours intact but the hours are gone from AssignmentByDay table.
Could anyone suggest what could have caused this so that we could avoid the samething happening for other projects? And Is there a way get those hours back to AssignmentByDay table?
We are on Project Server 2010 with August 2012 CU. We take a report on Actual Hours from MSP_EPMAssignmentByDay table.
One of our projects, which used to show a total of around 2000 hours, is now showing 0 hours in the report.
On further analysis, it was observed that the table MSP_TimesheetActual has all the actual hours intact but the hours are gone from AssignmentByDay table.
Could anyone suggest what could have caused this so that we could avoid the samething happening for other projects? And Is there a way get those hours back to AssignmentByDay table?
Regards Prasad