Hellow,
Project Server 2010: I have a project custom field that uses the Now() function as a part of the formula. I've noticed that the field is not re-evaluated in Project Center views, and you have to edit the project with Project Pro (not even PWA) to get the updated value.
Is that correct? Is there any workaround for this? Doesn't that lose the meaning of having a date-dependent calculated field.
Thanks,
Spyros