In older versions of Project Server a couple of project practices was given to me to ensure we don't pick up issues or corruption on the system. I want to know if these are still applicable for the 2013 environment
Do save the project plan to project server with unique characters in the Filename.
Do not leave empty lines on the project schedule in between tasks.
Do not add resources on summary tasks.
Do not put in link selected tasks on summary level.
--------------------------------
Then on Project Server config itself
Do not put in unique characters on Enterprise lookup field names or the lookup values as it screws up the Cubes
I will appreciate feedback on this , enjoy the weekend and those on weekend have a good one.
Willem