Actual Finish date disappears?

$
0
0

Hello all. I have a couple of files that have a recurrinig problem. The actual finish dates on tasks keeps getting cleared and reset to NA. The tasks are marked 100% complete, the actual finish date populates in the field, and the file is saved. Later when the file is opened the actual finish dates are NA but the % complete is still 100%.

Anyone see this behavior?

MSP2007 SP2, Oct 2010 CU and project server patched the same.