Project 2010 SP1, While posting updates to My Tasks, the information that I enter as Task Notes is not being moved to Task Notes History section. The task is assigned to only one user. I enter the Note and do a Send but the note never goes up to the "history" section, ie. the top part of the screen.
Also, since the notes do not got to the history, when the project is opened in Project Professional, the "new" note is not shown. Is there a permissions that needs to be set for this to happen correctly? It appears that this was working at one time but no more.