OK so I have been looking through the Reporting Database to figure a problem out.
We have a small number of resources (all with the calendar we use for all resources), who seem to be able to book time to a non-working day (in timesheet it isn't greyed out).
I then started looking at the tasks in the timesheet and suspect it's to do with the Projects and their Tasks but there is a lot of data to try and investigate through.
Does anyone have any tips or pointers as to what I am looking for?
TIA