Can you please tell me how to change the working times of an existing Onshore resource. He is an Onshore resource where working times are 8hrs per day. He already added in
resource pool, but his working times are wrongly set to 9hrs per day. I want to change only his working times to 8hours. Is this possible - There are two resource, for whom the calendar is the same but one resource can be allocated to work for 9 hours and
the other can be allocated to work for 8 hours?
↧