Hi,
I am relatively new to project server 2010.
I need the resource departments of the resources to be displayed at the task level for projects along with task name, %work complete, baseline start, baseline finish and resource names.
For the same, I have assigned a few users to their respective departments and added the resource department field to the assignment summary view under Project view (manage views).
The resource department field is displayed in the assignment summary view but it does not reflect any values. Could anyone please help me with this?
Thanks in advance,
Chinmay Rajput