In previous versions of project if you looked at the Resource Usage chart it would show you total actual hours per resource for the project plan currently open. However in Project 2010 it shows you total actual hours per resource across all projects. If you expand a resource it will then show a detailed view but you have to manually add each of the items they worked on for your desired project to get the total hours worked for just that 1 project. Is there a smart way to do this or to make it behave like it used to?
Thanks,
Trent