Hi,
We have implemented Project Server 2010. We have project managers (20 persons) that use Microsoft project 2010 and Project server 2010, and team members ( 100 persons) that only use Project server 2010.
We have a problem of different information between the plans in project and the tasks updated in project server. A team member update a task in the timesheet clicks "send Status" or "Send timesheet" , the project manager approved the
tasks in the Approval Center. The line Manager approved the timesheet. But when you open the project plan in the Microsoft project plan this plan doesn't have the last infomation and updates coming from the team members.
We go in the Approval Center and to the "History" , "Approval updates", and some approval are published, other approval are not published. And it's a huge problem to us, because we are working in this tool, 2 months, more than 100 persons, and I have a huge
list of no changes update in my projects.
I have one update in "error", Action "Rejected" says "The update was not applied because it contains invalid data".
And in the other hand, I suppose due to this unlink between project plans and timesheets, the team members suffer continues changes in their timesheets, and in the task updates they have sent, or they don't have the proper assignation to taks, in their timesheets.
I have a lot screenshots, but I don't Know how to put here.
Any Ideas? Any Help? We are living a nightmare with this... is there something wrong in the parametrization?
Thanks a lot for your help.
Carmen