NOTES: WSS; Project Server 2007
I may be wrong, but I was under the impression that the data used to populate PWA's view "Resource Availibility" was the "Work" data...
Now I have this problem where a resource is assigned to a Published Project, where the correct "actual" and "work" hours are reflected in the "Resource Assignments" view, but the data does not show up at all on the "Resource Availability" view...
Now I am being asked why is the data incorrect...
Example: Resource X worked on Project ABC from 3JAN2012-9JAN2012. The resource completed 40 hours of actual work, which was entered by the PM using Project 2007 Professional (Resource Usage/Task Usage View). Project ABC was
then published, and the project has since made it to 100% complete before today's date.
Resource Assignments shows: Work = 40 hours, Actual Work = 40 hours, and Remaining Work = 0 hours for the Task from Project ABC.
Resource Availibility does show that there was work for that project, but it does show work for that day/week/month of JAN2012 on other projects.
Options: Date Range = 1/1/2012 To: 1/13/2012 ; Units: Days
Include Proposed Bookings: (Check)
Can someone help me explain why?