Quantcast
Channel: Project Server General Questions and Answers forum
Viewing all 7942 articles
Browse latest View live

MSPS 2007: How to find team project association?

$
0
0

I have projects on MSPS 2007 that are connected to Team Projects (TFS). Can I get the association details in the database?

Actually, I need to make queries in the TFS database for some work items associated to a project in MSPS 2007. How to do this?


Does that helps?
--------------------------------------------------------
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”.
Thanks,
Kangkan Goswami |Technical Architect| Blog: http://www.geekays.net/
http://in.linkedin.com/in/kangkan


WBS lost after publishing project plan Project 2010

$
0
0

Hi everybody!

I have a problem: sometimes i lose wbs codes for some tasks after publishing project plan on the server.

Could you help me to understand the reason of it?

Thanks!

Resources on a project with Multiple Calendars not calculating correctly

$
0
0

I have a project using resources that work on different calendars, my default project calendar is none. I want to have each resource show with their appropriate work time and duration. I have tried to associate each taks to a unique calendar to no luck, any ideas?

I am using Project 2010.

Any ideas would be appreciated.

Doug

PS 2010 - Users are getting Inactivate during AD Synchronization

$
0
0

Dear Guys,

During the AD Resource Pool Synchronization some users are getting inactivated, although they are active in AD. What could be the reason behind this and how can we fix this?

Need Help.


Thanks


Mohsin Raza

losing flag settings

$
0
0

I am using Project Server V2010 SP1. 

I updated a schedule on the Server via my laptop.  In addition to making some date changes, I made some changes to a user defined flag that drives a filtered view.  I saved and closed the file on my laptop and as far as I am concerned I saved it up to the Server.  I then opened the same file from my desktop machine.  The file is now hosed since somehow the Server dropped most, but not all of the flag settings that drive that view.  I then went back to my laptop and opened the file from the cache version and everything appears fine.  Figuring that this was an issue of the cache on the desktop machine, I cleared the cache on that machine.  This made no difference.  I then went back to the laptop and published the file.  Still no help.  I don't dare wipe the cache on the laptop for fear of losing everything I've built.

We had a problem similar to this back in the spring and we applied a hotfix.  I thought the problem was resolved, but it appears to be back.  Stinking gremlins!

Suggestions, anyone?

Error in displaying the indicator

$
0
0

Hi All,

I am using PS 2007. I have two different PWA sites on this server. I have copied a custom field formula for Task indicator which works correctly on one site but on the other site I am recieving an Error. How is it possible? For your reference below is the formula that I have used:

IIf(ProjDateValue([Baseline Finish])=4294967295 Or ProjDateValue([Baseline Start])=4294967295 Or ProjDateValue([Start])=4294967295 Or ProjDateValue([Finish])=4294967295,4,IIf(ProjDateValue([Baseline Start])<Date() And ProjDateValue([Actual Start])=4294967295,5,IIf(ProjDateValue([Baseline Finish])<Date() And ProjDateValue([Actual Finish])=4294967295,6,IIf([Finish Variance]/IIf(ProjDurValue([Baseline Duration])=0,1,ProjDurValue([Baseline Duration]))>0.1,3,IIf([Finish Variance]/IIf(ProjDurValue([Baseline Duration])=0,1,ProjDurValue([Baseline Duration]))>0,2,1)))))

Please help!!


Cheers, Amit Wairkar

AddSingleUserMembershipInWss job failed

$
0
0

Project Server 2010, SP 2010

Anytime we edit any permissions or force an AD sync we are bombarded with the erro below:


Your AddSingleUserMembershipInWss job failed.  Its current state is FailedNotBlocking.  It was 0% complete.  It entered the queue at 06/14/2011 16:48:40.

 

To get more information about the job failure, please go to Project Web App.  Select Personal Settings from the left menu.  Then select My Queued Jobs.

 

The errors returned from the queue are as follows:

 Error ID: 26000

 

Detailed error below - send it to the administrator for more detailed troubleshooting.

 

<?xml version="1.0" encoding="utf-16"?>

<errinfo>

  <general>

    <class name="Queue">

      <error id="26000" name="GeneralQueueJobFailed" uid="9ab3e192-0d51-4eaa-a5d5-d0ec0051eb93" JobUID="bb98357f-f681-4a34-be6b-5d42a506ddc9" ComputerName="UMCSP" GroupType="AddSingleUserMembershipInWss" MessageType="AddSingleUserMembershipInWssMessage" MessageId="1" Stage="" />

    </class>

  </general>

</errinfo>

Project Permission in PWA 2010

$
0
0

I am seeing this error anytime some is taken out of a Project Permissions.

User Synchronization (Add Operation) for Project Web App App Root Site and Project Sites   [ERROR 7704 from the logs]

User Synchronization (Delete Operation) for Project Web App App Root Site and Project Sites   {Successful}

It happens maybe 1 out of every 4 times someone is added to a permission for a project.

Looks like the permissions are added or taken away, but the queue says otherwise.

General
Queue:
GeneralQueueJobFailed (26000) - AddSingleUserMembershipInWss.AddSingleUserMembershipInWssMessage. Details: id='26000' name='GeneralQueueJobFailed' uid='51e6dfde-9e17-4439-89f4-cb8555763e0a' JobUID='0601092a-f55f-4ee4-ba15-8130542d4d48' ComputerName='WDCDVWA66' GroupType='AddSingleUserMembershipInWss' MessageType='AddSingleUserMembershipInWssMessage' MessageId='1' Stage=''. For more details, check the ULS logs on machine WDCDVWA66 for entries with JobUID 0601092a-f55f-4ee4-ba15-8130542d4d48.


yubouybouy

Timesheet actuals vs MS Project actuals - problem

$
0
0

Hi All,

I have MSP 2010 with latest CU applied (June 2012 CU)

I’m using SEM. Tracking method: Hours of work done per period withForce project managers to use the progress reporting method specified above for all projects” option marked.

I also have marked Only allow task updates via Tasks and Timesheets

My tasks are manually scheduled. I’m reporting my hours using timesheet view.

If I understand those settings correctly any actual work changes, % Complete changes will be prohibited – am I right?

I’m asking this question because I have problem with replacing timesheet actuals with planned values and I’m not able to correct those problems easily.

Maybe someone have this same problem? When I’m trying to delete replaced actuals (+accept and publish) they come up again when I delete my timesheet.

This is old problem and after each CU I’m praying for a solution but I have still the same problems.

Please help J

 

no permission to read project server enterprise global file(project server 2010)

$
0
0

I am unable to open my projects with project professional from the PWA.please how can i resolve this?

It gives the error: you do not have sufficient permissions to perform the required action in project professional and the same applies for the PWA

can somebody please help?

Query Project server 2010 cube

$
0
0

Greetings.

Just a quick question about Project Server 2010.  I know that there is a cube that is processed each night and includes projects and risk data.

I have heard I can connect to the cube using the Microsoft SQL Server Analysis Services Datasource Type within SSIS.  I need to do this as I need to run a procedure to extract this data to another destination.

However, I'd like to access the data direct from the database rather than the cube.

is this possible? and if so, what database is the cube info stored in? 

Many thanks

How to import project plan available in particular location on desktop with ".mpp" extension to project server 2010 programatically.

$
0
0

hi,

Can any one suggest.

How to import project plan available in particular location on desktop with ".mpp" extension to project server 2010 programatically.


Thanks & Regards, Krishna

Project Server 2010 Custom Field Formula

$
0
0
I am looking for a formula for a custom field in Project Server 2010.  The formula should run like this:  When a project date runs beyond the Actual Finish date the color indicator should turn red.  If the date is less than 10-days or equal to the Actual Finish date the color to orange. If the date is less than 11-days than the Actual Finish date the color is green.  

Any help in setting this help would be appreciated.

Flag tasks with ‘local resources’ assigned

$
0
0

I’m using Project Professional 2010 SP1.

Problem I am trying to solve for: If a task has a ‘local resource’ assigned (i.e., not an enterprise resource) I want to flag the task in a view.  Although the Indicators column on the Resource Sheet displays the local resource icon, the Indicators column on other views do not. 

Suggestions?


Dave Shultz, PMP

Error when saving a file in PS 2007

$
0
0

Good afternoon,

A client of mine is interested in determining why some of the projects he is trying to save give this error (he is using PS 2007) get the following error:

"

The file cannot be opened

> Check that the file name and path are correct Check that the file

> format is recognized by Project

Project files save in version earlier that Microsoft Project 98 can't be opened."

We have a workaround to export to MPP or XML but he is interested in the cause so maybe he can avoid the inconvenience, or possible corruption, in the future.

Any suggestions are appreciated.

Jakc


Thanks, Jack


Costum field formula

$
0
0

I need to create a custom field with a formula in order to obtain information from another costum field who it is associated with a lookup table.


The custom field has a lookup table values ​​returns (AAA.BBB.CCC), and I need to have the BBB information in the new costum field. However the length of characters is variable.The only fixed information is point.

Can you help me plz...

   

Project server 2010: Process Status Column in Task Grid Query

$
0
0

Hi Guys,

Need a simple clarification on Process Status Column in Task Grid as to

What is the diff between ‘Completed’ and ‘manager Approved’ status?

how to upload projects into project server 2010 which got created from Microsoft Project 2010 Proffessional ( .mmp) and got uploaded to sharepoint site document library

$
0
0

 

hi

can any one suggest.

Projects which got created through Microsoft Project 2010 Proffessional  (.mpp) got uploaded into Sharepoint 2010 sites document library need update/create projects into project server 2010 programtically.


Thanks & Regards, Krishna

Build a SharePoint work flow for project server

$
0
0

Hi,

Is there a way to use a work flow that runs on a SharePoint 2010 list to create a project in project server from the list item. 

Chris

Why is MS Project 2010 not recognizing my Project Server 2010 Enterprise RBS settings?

$
0
0

We are using Project Server 2010, with RBS for our Enterprise Resource/user reporting, and Microsoft Project Professional 2010.

We create projects with generic resources and then the various team leads are suppose to go in and assign actual resources to the tasks. If this process is done using PWA enabled for editing, the limitation of only seeing resources that are decendants for your RBS works fine. A team lead cannot assign a resource from another team.

HOWEVER, since making mass changes etc is so much easier in MS Project 2010, the team leads prefer to use this method to replace the generic resource with someone from their team. BUT here comes the problem. The team lead opens MS Project 2010 with a default profile connecting them to Project server . The Open the project via the Enterprise Projects stored on Project Server 2010, They get a "message" that lists resources assigned to the project that do not report to this team lead which they acknowledge. However, when they get to the task that they are going to update, the WHOLE project team is shown and the Lead is able to select resources that do not report to him. Not error message or restriction occurs.

We have had individuals select names from the list who do not report to them and after they save > publish > closed; the task has two direct reports and a person not on their team (call this person not on team, Recource D). How can I stop leads from selecting people not on their team?  Eventually when Resource D tries to look at their tasks, an "unkown error" occurs because the Resource D (selected via MS Project 2010) is not considered a "true" Enterprise Resource by Project Server 2010.

Viewing all 7942 articles
Browse latest View live




Latest Images